    Question

    A can complete a certain work in 30 days. B is 20% more

    efficient than A. C can complete2/3  part of the same work in 8 days. A and B together complete 11/15 part of the work. The remaining work is completed by A and C together. In how many days was the entire work completed?
    A 13(1/5) Correct Answer Incorrect Answer
    B 13 Correct Answer Incorrect Answer
    C 14 Correct Answer Incorrect Answer
    D 14(2/5) Correct Answer Incorrect Answer

    Solution

    The correct answer is A