Question
A can do 1/5 of a work in 3 days and B can do the same work in 24 days. C can complete 40% of the work in 8 days. All three work together for x days, then A leaves the work, and B and C together complete the remaining work in x days. Find the value of
A can do 1/5 of a work in 3 days and B can do the same work in 24 days. C can complete 40% of the work in 8 days. All three work together for x days, then A leaves the work, and B and C together complete the remaining work in x days. Find the value of
x.
More Previous year papers Questions
- The average weight of 17 girls is 20 kg and that of 23 boys is 22 kg. Find the average weight of the class?
- What will be the value of the following expression? 0.25 ÷ 0.0025 × 0.025 × 25
- If a + b = 90° and a = 2b , then the value of 3 cos2a – 2 sin2b is equal to:
- Simplify the following.
- Two trains are travelling in the same direction on parallel tracks. Train A is travelling at 30 km/h and Train B is travelling at 60 km/h. If Train A is 40...
- If (4y –1) and (y + 4) both are factors of py² + 15y – q then:
- If 18 men can finish a work in 13 days. Then in how many days will 54 men finish the same work?
- A commodity is made of two metals, A and B, which cost ₹35 per kg and ₹40 per kg, respectively, in the ratio of 2 : 3. What is the cost (in ₹) of 12 kilogr...
- Pipe L can fill a pool in 30 hours and pipe M in 45 hours. If both the pipes are opened in an empty pool, how much time will they take to fill it?
- Two years after a couple's marriage, a son was born. Four years after the son's birth, the average age of the family is 28 years. Six years later, the sum ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)