      Question

      A, B and C can complete a piece of work in 3 days, 4

      days and 6 days, respectively. They get Rs.432 for completing the job. If A, B and C work together to complete the job, A’s share is:
      A Rs.72 Correct Answer Incorrect Answer
      B Rs.192 Correct Answer Incorrect Answer
      C Rs.108 Correct Answer Incorrect Answer
      D Rs.144 Correct Answer Incorrect Answer

      Solution

      The correct answer is B