Question
A, B and C can do a piece of work in 20 days, 30 days and 60 days respectively. If A works daily and on every third day B and C also work with A, then in how many days, will the work be completed?
More Previous year papers Questions
- Find cosθ using the given diagram.
- Anil deposited Rs.8,000 in a two-year fixed deposit scheme on compound interest compounded annually at 5% per annum. Find the maturity value of the fixed d...
- How can 378 mobile phones be shared equally in the students present in the classroom?
- The volume of a sphere is given by 130977 cm³ . Its surface area (in cm²) is:
- Find the value of X: (X3) ÷ 45 = 2025
- ₹7,140 is divided among A, B, C and D in such a way that the shares of A and B, B and C, and C and D are in the ratios of 2 : 3, 4 : 5 and 6 : 7, respectiv...
- Find the average of all the numbers between 21 and 70 which are divisible by 3 and leave the remainder 2.
- Which of the following fraction can be written as a Non-terminating decimal?
- Ravish has read 4/5 of a book while Soma has read only 5/8 of the book she is reading. Both, however, have another 120 pages of their respective books rema...
- A and B can complete a job together in 12.5 days; B and C can complete the same job together in 18.75 days, while C and A can complete the same job togethe...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)
1st day work by A = 3unit 2nd day work by A = 3unit 3rd day work by A+B+C=3+2+1 = 6unit Work done in 3 days is 3+3+6 = 12 unit Total time required to complete the work 3 x 5 = 12 × 5 15 days = 60unit In 15 days, the work will be completed.