A, B and C can do a piece of work in 20 days, 30 days
and 60 days respectively. If A works daily and on every third day B and C also work with A, then in how many days, will the work be completed?Solution
1st day work by A = 3unit 2nd day work by A = 3unit 3rd day work by A+B+C=3+2+1 = 6unit Work done in 3 days is 3+3+6 = 12 unit Total time required to complete the work 3 x 5 = 12 Ă— 5Â 15 days = 60unit In 15 days, the work will be completed.
Which one of the following is not a method of estimating the National Income of a country?
In the fiscal year 2022-23, what was the Year-on-Year (YoY) growth rate of India's services sector?
India is not part of which of the following?
Farming large areas with minimal labor and capital inputs is known as:Â Â
Which statements correctly describe the roles and responsibilities of the Reserve Bank of India (RBI)?
Statements:Â
1. The RBI formulates...
What does an Inverted Duty Structure imply under the GST framework?Â
The Monetary and Credit Policy is announced by which of the following?Â
Which of the following are the specialized wings under the NITI Aayog:
i. Â Research Wing
ii. Â Development Wing
iii. Team I...
What is the definition of a supply chain in a business context?
Which one of the following pairs is correctly matched?