Question
A, B and C can do a piece of work in 20 days, 30 days and 60 days respectively. If A works daily and on every third day B and C also work with A, then in how many days, will the work be completed?
More Previous year papers Questions
- On what sum of money will the difference between the simple interest and compound interest (Compounded annually) for 3 years at 5% per annum be ₹15.25?
- Find the number of integers between 50 and 500 which are divisible by 7.
- A line graph is given below which shows the number of cars sold by seller A and seller B on five days. Find the number of cars sold on Sunday by A and ...
- Find the value of x in the following equation:
- A glass jar contains 6 white, 8 black, 4 red and 3 blue marbles. If a single marble is chosen at random from the jar, what is the probability that it is bl...
- Simplify
- A student scores 75% in a test and gets 30 marks more than another student who scored 60%. What is the maximum marks in the test?
- The average weight of 7 people increases by 5 kg when a new person comes in place of one of them weighing 55 kg. What is the weight of the new person?
- At a Yoga center, 60% of the members are men and 40% of the members are women. If the average age of the men is 55 years and the average age of the women i...
- In ΔPQR,PQ=QR and O is an interior point of ΔPQR such that ∠ OPR= ∠ ORP . Consider the following statements: (i) ΔPOR is an isosceles triangle. (ii) O is t...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
1st day work by A = 3unit 2nd day work by A = 3unit 3rd day work by A+B+C=3+2+1 = 6unit Work done in 3 days is 3+3+6 = 12 unit Total time required to complete the work 3 x 5 = 12 × 5 15 days = 60unit In 15 days, the work will be completed.