A and B can complete a task in 6 and 8 days,
respectively. They work on alternate days, with A starting the task on the first day. How many days will it take them to complete the task?Solution
Work done by A in a day =1/6 Work done by B in a day = 1/8 Work done in two days = 1/6+1/8 =7/24 Work done in 6 days = 21/ 24 Work remaining = 1/8 Time required by A = ¾ Total days =6+3/4=27/4 Time required to complete the entire work = 27/4days