A work can be completed by P and Q working separately in
12 and 18 days, respectively. But they work on alternate days beginning with P. How many days will it take to complete the work?Solution
 Let the total work = LCM of 12 and 18= 36 A can complete work 12 days Work does in one day= 36 /12 = 3 unit B can complete work 18 days 36 Work done in one day=36/ 18 = 2 unit As they work for alternate days, In 2 days, work completed is 2 days = 3 unit + 2 unit 2 days =5 unit 14 days =35 unit The remaining work = 36-35= 1 On the last day, A has to work= days Total days= 14 days +1/3 days= 14 (1/3)days
A loan is categorised as NPA when its interest or principal repayment become overdue for more than 180 days
Which number will come at the end of the number series?
85, 77, 70, 64, 59, 55, _____?
From which state does the distinguished tennis player Rohan Bopanna, who recently retired, originate?
P-Notes are instruments issued by registered FII to overseas investors, who wish to invest in the Indian stock markets without registering themselves w...
Which of the following cities is not situated at the river bank of the Ganges?
In which year were the Operation Shakti nuclear tests conducted by India?
The Government of India launched the PRASAD (Pilgrimage Rejuvenation And Spiritual Augmentation Drive) scheme in the year ____ under the Ministry of Tou...
In which of the following years, progressive liberalisation of the Indian economy was first initiated?Â
Which of the following is correct?
The largest state of the country India is?