Question
While solving a question, Suhas mistakenly took a number
as the dividend which was 10% less than the original dividend. He also mistakenly took a number as the divisor which was 20% less than the original divisor. If the correct quotient of the original question was 24 and the remainder was 0, assuming that there is no error in his calculation, what quotient did Suhas obtain?Solution
Let the original dividend (D) be 100 units. The correct dividend (D) and divisor (d) result in a quotient of 24 and remainder 0 (i.e., D = 24d), Suhas erroneously took 90% of the dividend (0.9D) and 80% of the divisor (0.8d). The quotient (Q) of these two erroneous values is: Q=0.9D/0.8d. Substitute D = 24d Q = 0.9 x 24d/0.8d Q = 21.6/0.8 Â Q = 27.
A and B together can finish a work in 10 days. If A alone can finish it in 25 days, in how many days can B alone finish it?
A man, a woman and a boy can do a work in 4, 8, 16 days respectively. How many boys were required with 1 man and 1 woman to complete the same work in 1/...
A man is thrice as fast as a women and a woman is twice as fast as a boy. If all of them can do a work in 18 days. than a boy can do the work in?
x men can finish a work in y days. 0.9x women can finish 1/3rd of the same work in (y - 8) days. If 0.8x women can complete 1/3rd work in 36 days. Find ...
'Ramesh' can complete a work in 40 days. He started the work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. F...
A and B finish a job together in 36 days, while B and C together finish it in 48 days. The trio completes 75% of the job in 18 days. In how many days wi...
There is enough food in a camp to last for 50 days if each of the 40 soldiers present at the camp eat 2 times a day. After 20 days, 40 more soldiers jo...
- Suppose D, E and F can do a piece of work individually in 18, 27 and 36 days respectively. If they combine and work for 4 days, what percentage of work wou...
- A builder employed 12 workers to complete a job in 18 days. But after 8 days, 4 workers quit. How many more days will be required to complete the remaining...
Twenty laborers can complete a piece of work in 12 days. If 20 laborers started working and after 3 more days, additional laborers joined to complete th...