      10 men can do a work in 25 days. After 12 days of work,

      3 more men were engaged to finish the work. The number of days required to complete the remaining work is:
      A 10 Correct Answer Incorrect Answer
      B 8 Correct Answer Incorrect Answer
      C 6 Correct Answer Incorrect Answer
      D 12 Correct Answer Incorrect Answer

      Solution

      ATQ- 10×25 =(10×12) +(13×a) 250 =120+13a 13a =130 A = 10days.