Question

X can do a certain work in 84 days. Y in 50% less efficient than X while Z takes 28 days to do the same work. To complete the work, Y started the work, X joined him after 3 days and Z joined them after 7 days from the beginning. For how many days did Z work to complete the work?

A 17
B 14
C 16
D 15