Question
X can do a certain work in 84 days. Y in 50% less
efficient than X while Z takes 28 days to do the same work. To complete the work, Y started the work, X joined him after 3 days and Z joined them after 7 days from the beginning. For how many days did Z work to complete the work?Solution
1 Day work of X = 1/84 th part of work 1 Day work of Y = 1 /168th part of work 1 Day work of Z = 1/28 the part of work 1 1 Day work of X and Y together =1/84 + 1/168 = 1/56 th part of work 1 Day work of X, Y and Z 1 together = 1/84 +1/168 +1/28= 3/56th part of work For 3 days, Y worked alone and completed = 3 x 1/168 =1/56th part of work 1 For next 4 days, X and Y worked together and completed = 4 ×1/56 =1/14 the part of work Now, remaining work after 7 days
Which cup is associated with football?
Which of the following sports is associated with the term 'Time trial'?
Who was selected as the torchbearer from India for the 2024 Paris Olympics?
At the 1936 Berlin Olympics, Jesse Owens won four gold medals in which sport?
Challenger Trophy is related to which of the following sports?
What is the edition number of the ICC Women’s T20 World Cup that commenced in Sharjah, UAE?
What program aims to promote Olympic values through sport among children in India?Â
RanjiTrophy is related to which sports?
Sudirman Cup is related to
What is the title of the short film made by the Sports Authority of India on the athletes participating in the Asian Games?