Worker A is thrice as efficient as worker B. They can
together finish a task in 18 days. How many days will A alone take to finish the work?Solution
A       B 3       1 (Efficiency). When he works together – 4 =18 1=72 A alone take to finish work = 72/3=24 days.
What is the latest horticulture production (in million tonnes) for the year 2024-25 as per the 2nd Advance Estimate?
The estimated total pulse production for 2024-25 (3rd Advance Estimate) was:
The Ganga Kalyan Yojana is for:
Fresh water fishes which have a great food value are :
The Minimum Support Price (MSP) approved by the Cabinet Committee on Economic Affairs for wheat for the 2025-26 rabi marketing season is ____ rupees pe...
Optimum seed rate for pigeon pea or red gram is
The Oil webinar on balanced oil consumption highlighted that India faces a 'triple burden of malnutrition'. Which option correctly represents all three ...
What is the number of the latest installment of the PM-KISAN scheme, and from which location was it released?
Ragi is rich source of
Microbial decomposition of organic matter is called: