Question
A and B together can complete a certain work in 54 days.
They work together for 12 days. The remaining work was completed by A, B and C together in 28 days. If the work done by B in 6 days is equal to the work done by C in 9 days, then A alone can complete two-thirds of the work in ________ days.Solution
The correct answer is A