      A and B working separately can finish a work in 15 days

      and 20 days, respectively. If they work on alternative days, A starting first, and if the work goes on for 8 days, what part of the work will be left unfinished?
      A 7/60 Correct Answer Incorrect Answer
      B 3/5 Correct Answer Incorrect Answer
      C 8/15 Correct Answer Incorrect Answer
      D 1/4 Correct Answer Incorrect Answer

      Solution

      The correct answer is C