      Question

      Rina can complete a piece of work in 6 days while Seema

      can do the same work in 9 days. If they both work together, then how many days will be required to finish the work?
      A 4 days Correct Answer Incorrect Answer
      B 10 days Correct Answer Incorrect Answer
      C 7.3 days Correct Answer Incorrect Answer
      D 3.6 days Correct Answer Incorrect Answer

      Solution

      The correct answer is D

      Practice Next