Question

    It takes 8 people working at equal rates to finish a

    work in 96 days. How long will 6 workers take for the same work?
    A 124 days Correct Answer Incorrect Answer
    B 125 days Correct Answer Incorrect Answer
    C 128 days Correct Answer Incorrect Answer
    D 122 days Correct Answer Incorrect Answer

    Solution

    8 people takes 96 days to complete the work. Total work = Number of men × Time taken Total work = (8 × 96) units Time taken by 6 worker = (8 × 96)/6 = 128 days