Question
Time taken by pipes 'X', 'Y' and 'Z' to fill a tank is
48 minutes, 80 minutes and 60 minutes respectively. All the pipes are opened together. 'X' is closed after 't' minutes, and 'Y' is closed (2t - 1) minutes before the tank is filled. If the tank is filled in 35 minutes, then determine the value of 't'.ΒSolution
ATQ, Let the total capacity of tank be 240 litres (LCM of 48, 60 and 80) Efficiency of 'X' = (240/48) = 5 litres/minute Efficiency of 'Y' = (240/80) = 3 litres/minute Efficiency of 'Z = (240/60) = 4 litres/minutes So, (5 + 3 + 4) Γ t + (3 + 4) Γ (35 - t - 2t + 1) + 4 Γ (2t - 1) = 240 Or, 12t + 252 - 21t + 8t - 4 = 240 Or, 't' = 8
Neha and Priya are assigned a piece of work. Neha can complete 8 units of work each day, while Priya can finish the whole task alone in 32 days. If the ...
Anu can finish 25% of an assignment in 10 days, whereas Tanya can do 30% in 12 days. Anu works on it for 16 days and leaves. How long will Tanya take to...
βMβ is 60% more efficient than βNβ. βNβ started the work alone and worked for 12 days and after that βNβ is replaced by βMβ. If the ...
Efficiency of A, and B are in the ratio of 2 : 3. If both can do a work together in 60 days. Find out how much days A will take to complete the work alone?
- 45 people can repair a road in 10 days working 6 hours a day. In how many days can 30 people working 6 hours a day complete the same work?
Ajay and Vijay together can paint a piece of furniture in 11 days. Vijay and Chirag together, as well as Ajay and Chirag together...
Twenty laborers can complete a piece of work in 12 days. If 20 laborers started working and after 3 more days, additional laborers joined to complete th...
A can complete `1/4` of a work in 6 days and B can complete `2/5` of the work in 12 days. In how many days can both A and B together complete the work?<...
Two men A and B started a job in which A was thrice as good as B and therefore took 60 days less than B to finish the job. How many days will they take ...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?