Question
The question consists of four statements numbered “I,
II, III and IV” given below it. You have to decide whether the data given in which of the following statements alone is not sufficient to answer the question. "Vishika purchased two items, 'Nailpaint' and 'Lipstick,' and managed to achieve a 28% profit after selling both items. We want to determine the cost price of item 'Lipstick.' Statement I: Item 'Nailpaint' is priced 60% higher than its cost price but is sold at a 20% discount. The average cost price of both items is Rs. 600, and the selling price of item 'Lipstick' is Rs. 640. Statement II: The selling price ratio of item 'Nailpaint' to item 'Lipstick' is 7:5, and item 'Nailpaint' is sold with a 28% profit. The average selling price of both items is Rs. 768. Statement III: Both items 'Nailpaint' and 'Lipstick' are sold with a 20% discount each. Item 'Nailpaint' is marked Rs. 420 above its cost price, and its marked price is Rs. 320 more than that of item 'Lipstick.' The cost price of item 'Nailpaint' is Rs. 700. Statement IV: A profit of Rs. 196 is made on the sale of item 'Nailpaint,' and a profit of Rs. 140 is made on the sale of item 'Lipstick.' The cost price of item 'Nailpaint' is 40% higher than that of item 'Lipstick.'" Now, you need to determine if each statement, individually or in combination, provides enough information to calculate the cost price of item 'Lipstick.'Solution
ATQ, Let we can asume that Item 'Nailpaint'= 'A' and Item 'Lipstick'= 'B' Then, Statement I: Let, cost price of article ‘A’ is Rs.‘x’ Selling price of article ‘A’ = 0.80 × 1.60 × x = Rs. 1.28x Selling price of article ‘A’ = 1.28 × 2 × 600 – 640 = Rs. 896 So, 1.28x = 896 Or, x = 700 Cost price of article ‘B’ = 2 × 600 – 700 = Rs. 500 So, data in statement I alone is sufficient to answer the question Statement II: Selling price of both articles together = 768 × 2 = Rs. 1536 Cost price of both articles together = 1536/1.28 = Rs. 1200 Selling price of article ‘A’ = 7/12 × 1536 = Rs. 896 Cost price of article ‘A’ = 896/1.28 = Rs. 700 Cost price of article ‘B’ = 1200 – 700 = Rs. 500 So, data in statement II alone is sufficient to answer the question Statement III: Marked price of article ‘A’ = 700 + 420 = Rs. 1120 Selling price of article ‘A’ = 0.80 × 1120 = Rs. 896 Marked price of article ‘B’ = 1120 – 320 = Rs. 800 Selling price of article ‘B’ = 0.80 × 800 = Rs. 640 Cost price of both articles together = (896 + 640)/1.28 = Rs. 1200 Cost price of article ‘B’ = 1200 – 700 = Rs. 500 So, data in statement III alone is sufficient to answer the question. Statement IV: Let, cost price of article ‘B’ is Rs. ‘y’ So, cost price of article ‘A’ = 1.40 × y = Rs. 1.4y So, 1.28 × (y + 1.4y) = (y + 196 + 1.4y + 140) Or, 3.072y = 2.4y + 336 Or, 0.672y = 336 Or, y = 500 So, data in statement IV alone is sufficient to answer the question.
A alone can complete a work in 18 days and B alone can complete it in 27 days. They work together for 6 days and then B leaves. In how many more days wi...
- Rahul does half the work done by Karan in 2/3 of the time. If they together can complete the work in 14 days, how much time will Karan take to complete the...
‘A’ alone can do some work in 20 days. ‘B’ and ‘C’ together can do the same work in 15 days. If ‘B’ is half as efficient as ‘A’, the...
Ashish and Anil can do a piece of work in 18 days and 24 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete th...
Akhil and Nikhil together can complete a work in 9 days while Nikhil alone takes 12 days to complete 50% of the work. If the efficiency of Sachin is 20%...
- 45 engineers working 5 hours a day take 15 days to complete a project. How many engineers working for 4 hours a day are needed to complete three times the ...
A, B, and C can complete a job in 15, 20, and 30 days, respectively. They start the work together but after 3 days, A leaves. Then, B works alone for 5...
P and Q together can finish a task in 72 days while Q and R can do it in 48 days. If P worked for 18 days, Q worked for 30 days, and then R finished the...
- 'Amit', 'Ravi', and 'Neha' can finish a piece of work in 66, 99, and 132 days respectively. They all started the work, but Amit left 8 days before the work...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alo...