    Question

    What notice period must the Board give to a Developer

    before suspending the letter of approval under Section 10(3)?
    A 1 month Correct Answer Incorrect Answer
    B 3 months Correct Answer Incorrect Answer
    C 6 months Correct Answer Incorrect Answer
    D No notice required Correct Answer Incorrect Answer
    E 15 days Correct Answer Incorrect Answer

    Solution

    Section 10(3) mandates a minimum three months’ written notice to the Developer stating grounds for proposed suspension and considering any cause shown within that period.