      Within what time frame must the Central Government

      constitute the Board of Approval after commencement of the SEZ Act?
      A 7 days Correct Answer Incorrect Answer
      B 30 days Correct Answer Incorrect Answer
      C 15 days Correct Answer Incorrect Answer
      D 3 months Correct Answer Incorrect Answer
      E 6 months Correct Answer Incorrect Answer

      Solution

      Explanation: Section 8(1) requires the Central Government to constitute the Board of Approval by notification within 15 days of commencement of the Act.