Question

A agreed to deliver a critical machine part to B's factory by 1 June. A, unaware that B had no spare part, delivered it on 10 June. B sued A for the loss of profits of the factory during the idle period. Under Section 73 of the Indian Contract Act 1872, B is entitled to -

A double the value of the machine part as liquidated damages for the delayed delivery
B no compensation at all, since a delayed delivery leaves the buyer without any remedy
C the full loss of profits, because that loss naturally flowed from the breach of the contract
D compensation only for loss arising naturally in the usual course, or which A knew when the contract was made
E loss of profits, as the idle factory was a special circumstance apparent to every reasonable supplier