A system has estimated components of 5 KLOC, 10 KLOC and 15 KLOC. If a simple size-based productivity estimate is 20 LOC/person-month, approximately how many person-months are required?

A 1500 person-months
B 100 person-months
C 3000 person-months
D 1000 person-months
E 750 person-months