Question
A system has estimated components of 5 KLOC, 10 KLOC and 15 KLOC. If a simple size-based productivity estimate is 20 LOC/person-month, approximately how many person-months are required?
More Software Engineering and Web Technology Questions
- A field accepts integer input between 1 and 100 (inclusive). A tester selects the values 0, 1, 100, and 101 for testing. Which testing technique is this?
- In the Basic COCOMO (Constructive Cost Model) estimation model, which factor is the primary input used to estimate software development effort?
- What are 'Design Patterns' in software engineering?
- Which software development methodology emphasizes iterative and incremental development, close team collaboration, and delivering working software in short...
- A software team modifies a deployed application specifically to fix a bug reported by a customer, where the reports module produces incorrect totals under ...
- Requirements change frequently; working increments are delivered every two weeks with continuous customer feedback. Which approach fits best?
- What is refactoring?
- Which of the following best describes a core principle of the Agile software development methodology?
- A computer system has a cache memory with an access time of 10 ns and a main memory with an access time of 100 ns. If the cache hit ratio is 95%, what is t...
- In the traditional Waterfall model of software development, which is the correct sequential order of phases?
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)