Indian Overseas Bank (IOB) has introduced a scheme that lets customers choose any name as their savings account number with the bank. The scheme called ‘My Account My Name’ will be available at all 49 regional offices of the IOB in India. As per the scheme, the account name can be a combination of seven letters, or seven numbers, or seven alphanumeric only like AJIT007, PRADHAN, or 2424707 etc. Customers will not be required to remember their 15 digits account numbers. To begin with, the scheme is available for IOB SB HNI and IOB SB SALARY account customers.
‘X’ can complete a job in 30 days. ‘Y’ is 50% more efficient than ‘X’. How long will they take to finish 75% of the work together?
...Anil and Ashish receive Rs.2200 for work of 8 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
- Rahul does half the work done by Karan in 2/3 of the time. If they together can complete the work in 14 days, how much time will Karan take to complete the...
A can fabricate a divider in 15 days , while B alone can assemble it in 25 days, If they construct it together and get an installment of Rs 7000, then f...
'A' is capable of completing a specific task on their own in 20 days. 'B' can independently handle 60% of the same task in 18 days. If 'A' and 'B' colla...
P and Q individually can complete the work in 26 days and 39 days respectively. If the time taken by R alone to complete the work is 1.25 times the time...
30 workers working 8 hours daily can finish a job in 20 days. Find the time needed by 20 workers working 12 hours daily to finish the same job.
Komal and Seema individually can complete a task in ‘3a’ hours and ‘7a’ hours respectively. If they together can complete (2/3)rd of the work in...
A and B together can complete a task in 12 days, while A alone can complete the same task in 20 days. If A and B start the work together, but B leaves a...
A can do a piece of work in 12 days, while B alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 d...