The Aravalli mountain range is located in western India and runs for about 800 kilometers in a northeastern direction across the states of Gujarat, Rajasthan, Haryana, and Delhi. Aravali range acts as the water divide between Narmada and Ganga. It is a barrier in transport and also acts as a water divider.
A can do a piece of work in 21 days and B in 28 days. If they together work on it for 5 days, then the fraction of the work that is left is :Β Β
'Zara' is capable of finishing a specific task in 60 days. On the other hand, 'Armaan' takes 40% more time than 'Zara' to complete the same task, while ...
βPβ is 20% more efficient than βQβ. βPβ can do a piece of work in 15 days. They begin the work together, but βQβ leaves after 6 days. Th...
A2 type ‘P’ pipes can fill a tank in 450 hours, while B2 type ‘Q’ pipes can fill the same tank in 6...
A boy(labour) was appointed by a manager on the term that he would be paid Rs 55 for each day of his work but would be fined at the rate of Rs 5 per day...
Amit', 'Bhanu', and 'Chintu' can finish a piece of work in 51 days, 85 days, and 102 days respectively. They all begin working together on the task, but...
Working individually, 'A' can finish 60% of a task in 18 days, and 'B' takes 15 days longer than 'A' to complete the entire task. However, 'B' and 'C' w...
- 50% of the work done by Meena in 2 days is equal to 25% of the work done by Lata in 5 days. If Meena can complete the job alone in 10 days, then how long w...
A takes 32 days to complete a work while B can complete the same work in 12 days less than A. If C can complete 25% of the work in 12 days, then find th...
βPβ alone can paint a house in 18 days, while βPβ and βQβ together can do it in 12 days. If βQβ started the work and left after 6 days, ...