Saurabh can complete a piece of work in 20 days. He worked for 5 days and left. Anirudh completed the remaining work in 12 days. If both had done the ...
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed b...
Nikhil and Rohit together can complete a job in 105 days 8 minutes, while Rohit and Suresh together can finish the same job in 70 days 5 minutes. If Sur...
Ram can produce 5 pots in a day. Rahul is 40% faster than Ram in pot-making. Together, they work for a period of 55 days, resulting in the production of...
A does 1/2 work and B does 3/4 work in the same time. Difference between number of days taken by A and B to work alone to complete the work individually...
P, Q & R can finish a work in 10 days, 15 days, and 20 days, respectively, working alone. P and Q work on the first day, P and R work on the second day,...
A and C together can paint a wall in 18 days. If C takes 36 days to do it alone, and C works for 27 days after A leaves the job, what is the percentage ...
40 men take 15 days to finish some work. If the work is to be finished in 8 days, then how many additional men should be hired?
'Ankit' can complete some work alone in 35 days. 'Amit' is twice as efficient as 'Sumit' and four times as efficient as 'Ankit'. If 'Ankit' and 'Sumit' ...