A work can be completed by βAβ and βBβ, alone in 12 days and 18 days, respectively. Find the number of days taken by βCβ to complete the sam...
Pβs 3 days work is equal to Qβs 4 days work. If P and Q together can complete the work in 32 days then how much time Q will take to complete 75% of ...
Aman, Arun and Abraham can complete a work in 12, 20 and 24 days respectively. They all start working together. Aman left the work 1 day before its comp...
Pβs 3 days work is equal to Qβs 5 days work. If P and Q together can complete the work in 30 days then how much time Q will take to complete 75% of ...
10 masons can build a wall in 15 days by working 8 hours per day. How many masons are required to build the wall in 10 days by working 12 hours per day?
βAβ can complete a work in 15 days and is 50% more efficient than βBβ. βAβ and βBβ start working together and βAβ leaves after 8 day...
Pβs 5 days work is equal to Qβs 6 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 60% of ...
‘A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in ...
Anand and Manav can collaboratively finish a task in {40/3} days, while Anand alone requires 24 days to complete the same task. Given that Prachi's effi...
A set of Q men can complete a work in 20 days, while (Q+4) women can complete the same work in 28 days. If 9 men and 13 women together can finish the sa...