    Question

    X and Y can complete a piece of work in 8 days and 12

    days, respectively. If they work on alternate days, with X working on the first day, how long will it take the duo to complete the same work?
    A 9(2/5) Correct Answer Incorrect Answer
    B 9(3/5) Correct Answer Incorrect Answer
    C 9(2/3) Correct Answer Incorrect Answer
    D 9(1/2) Correct Answer Incorrect Answer

    Solution

    The correct answer is D