Question
Ratio of the work done by P, Q and R in one day is 8:6:9
respectively. They all together can complete the work in 37 days. Q and R worked on it for 21 days. In how many days P will complete the remaining work.Solution
Let total amount work be = 37 x 23 = 851 units Amount of work done by Q and R in 21 days = 21 x 15 = 315 units Amount of work left = 851 β 315 = 536 Required time = 536/8 = 67 days