Ratio of the work done by P, Q and R in one day is 4:2:5
respectively. They all together can complete the work in 35 days. Q and R worked on it for 23 days. In how many days P will complete the remaining work.Solution
Let total amount work be = 35 x 11 = 385 units Amount of work done by Q and R in 23 days = 23 x 7 = 161 units Amount of work left = 385 – 161 = 224 Required time = 224/4 = 56 days
- Michel Talagrand, recipient of the 2024 Abel Prize, is a mathematician from which country?
Who discovered penicillin?Â
Identify the correct statements about Indian Railways:
1. Indian Railways is the world’s largest railway system under single management.
- Longitudinal waves cannot travel through which of the following?
Consider the following statements with reference to the ‘BCCI Naman Awards 2025’:
1. Sachin Tendulkar was conferred with the ‘Col. C.K. Nay...
- In the Indian legal framework, the right to education is classified as which type of right?
- Which of the following cell organelles are correctly matched with their respective functions?
- India recently delivered the second batch of BrahMos supersonic cruise missiles to which country?
Which of the following pairs is correctly matched?
NISAR Satellite is jointly developed by which space organizations?