📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    ⚡ Month End Offer- Few Hours Left Flat 55% Off On All Courses!! Coode - OCT55 Enroll Now ⚡
    00:00:00 AM Left

    Question

    What was the revised completion timeline for the

    Vizhinjam International Seaport project as per the supplementary concession agreement?
    A 2035 Correct Answer Incorrect Answer
    B 2045 Correct Answer Incorrect Answer
    C 2028 Correct Answer Incorrect Answer
    D 2025 Correct Answer Incorrect Answer
    E 2030 Correct Answer Incorrect Answer

    Solution

    The Vizhinjam International Seaport project’s new completion timeline is 2028, accelerated from the earlier target of 2045.

    Practice Next
    ask-question