What is the installed capacity of the Punatsangchhu-I
Hydroelectric Project discussed during IndiaâBhutan power sector talks?ÂSolution
The Punatsangchhu-I Hydroelectric Project has an installed capacity of 1,200 MW. Discussions focused on early commissioning of the project to enhance power generation capacity and strengthen bilateral energy cooperation. Â
Collateral fee loan limit for short term agri-credit has been raised from Rs. 1.00 lakh to Rs. ____lakh.
What is the Minimum Support Price (MSP) for Paddy (Common) for the year 2025-26?
On World Environment Day 2025, Prime Minister Narendra Modi launched which tree plantation campaign?
What is the latest horticulture production (in million tonnes) for the year 2024-25 as per the 2nd Advance Estimate?
âCrop loggingâ is a method of:
Which crop recorded the highest production increase in 2024-25 compared to 2023-24?
An Enquiry into the Nature and Causes of Wealth of Nationsâ is the book of economist
The main objective of intercropping is to
ICAR - sugarcane breeding institute is one of the oldest research institute and is situated in
Chemosterilants are the chemical compound used to control economically destructive or disease-causing pests by causing