    What is the total cost of the fisheries processing

    cluster project in Karaikal under PMMSY?
    A ₹320.15 crore Correct Answer Incorrect Answer
    B ₹312.50 crore Correct Answer Incorrect Answer
    C ₹348.89 crore Correct Answer Incorrect Answer
    D ₹330.40 crore Correct Answer Incorrect Answer
    E ₹355.20 crore Correct Answer Incorrect Answer

    Solution

    The Karaikal fisheries processing cluster , set up under PMMSY , has a total project cost of ₹348.89 crore , with ₹298.34 crore funded by the Centre . The project will be linked to the Thengaithittu fishing harbour , helping to strengthen Puducherry’s fisheries economy.