A and B together can complete a work in 7.2 days, while B and C together can complete the same work in 12 days. If A is twice efficient than C, then fin...
Pawan completes 40% of a task in 6 days. His efficiency is 100% greater than Qureshi's. How many days will it take for both Pawan and Qureshi, working t...
- 8 men working for 5 hours a day can complete a work in 28 days. If 16 women are employed to work, then find how many hours a day they have to work to compl...
‘A’ and ‘B’ can complete a certain work in 18 days and 10 days, respectively. They started working together and worked till completion of the wo...
- 'Ankit', 'Manish', and 'Tarun' together can complete a work in 25 days. 'Ankit' and 'Manish' together can complete the same work in 75 days. 'Tarun' alone ...
Aman, Bishnu, and Chintu can each complete 20%, 25%, and 60% of the work in 4 days, 9 days, and 27 days, respectively. If all thr...
A and B can complete a work together in 36 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed ...
A takes 32 days to complete a work while B can complete the same work in 12 days less than A. If C can complete 25% of the work in 12 days, then find th...
Ajay and Vijay can finish a task in 9 days working together. Charu, who is twice as efficient as Vijay, can complete the task alone in 18 days. If Ajay ...