India recently rejected a statement issued by the OIC on a judgment of the Supreme Court upholding the abrogation of Article 370 that guaranteed special status to Jammu and Kashmir. It is the second-largest intergovernmental organization in the world after the United Nations, with a collective population reaching over 1.8 billion. It was established in September 1969 upon a decision of the historical summit that took place in Rabat, Kingdom of Morocco, on September 25, 1969, as a result of the criminal arson of Al-Aqsa Mosque in occupied Jerusalem.
‘P’ who is 20% more efficient than ‘Q’ can finish a work in 15 days. ‘P’ and ‘Q’ start working together, but ‘Q’ leaves after 6 days...
A and B can complete a task together in 14 days, while B alone takes 28 days to finish it. A began working alone and left after ‘x’ days, after whic...
A, B, and C can complete a job in 15, 20, and 30 days, respectively. They start the work together but after 3 days, A leaves. Then, B works alone for 5...
Raman can complete a certain task by himself in 30 days. Both Raman and Rajat worked together to finish this task, earning a combined wage of Rs. 5,850....
Three workers P1, P2 and P3 got work from the contractor. In 30 days, ‘P1’ completed 30% of work. ‘P2’ is 20% less efficient tha...
'Ajeet' has an efficiency that is 40% lower than 'Chirag's, where as 'Bittu' is 20% more efficient than 'Chirag'. The time difference between 'Bittu' an...
Anil and Ashish receive Rs.1200 for work of 8 days. If Anil is 5 times efficient than Ashish, then find the daily wage received by Ashish.
‘A’ and ‘B’ can complete a certain work in 12 days and 24 days, respectively. They started working together and worked till completion of the wo...
A can complete a piece of work in 10 days. B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many...
Choose the statements that correctly show two workers taking 6 hours and 9 hours to complete a task, respectively.