Question
Given that the standard hours are 600, actual hours are
500, the standard labor rate is ₹2.5 per hour, and the actual labor rate is ₹2.2 per hour, what is the Labor Rate Variance?Solution
The Labor Rate Variance is calculated by multiplying the difference between the standard rate and the actual rate by the actual hours worked. In this case, the variance is ₹150, and it is favorable because the actual rate is lower than the standard rate. (2.5-2.2) * 500 = 150(F)
If 20 – 10 means 200, 8 ÷ 4 means 12, 6 × 2 means 4, then 100 – 10 × 1000 ÷1000 + 100 × 10 =?
Four girls A, B, C and D, and four boys P, Q, R and S, are sitting around a round table facing the centre.
i. No two girls or boys are sitting ne...
Seven people, A, B, C, D, E, F and G, are sitting in a straight row, facing north (not necessarily in the same order). Only 2 people sit to the right of...
Identify the figure that completes the pattern (rotation is NOT allowed).
In a certain code language, ‘paint the wall’ is written as ‘jh dw qp’ and ‘wall of honour’ is written as ‘fh ut dw’. How is ‘wall’ w...
Seven boxes A, B, C, D, E, F and G are kept one over the other, but not necessarily in the same order. There are exactly 3 boxes between A and C. Box E ...
Change the question mark with the option that follows the applied logic in the first pair.
209 : 55 :: 579 : ??
Select the correct mirror image of the given figure when the mirror is placed at MN as shown below.
What should come in place of the question mark (?) in the given series?
10 27 45 64 84 ?
Pointing out to a person in a photograph, Sonal said, "She is the daughter of the daughter of the woman who is the mother of the husband of my mother." ...