Question

When does the extension of the Date of Commencement of Commercial Operations (DCC

  • O not be considered as restructuring?
A If the revised DCCO falls within the period of one year from the original DCCO.
B If the revised DCCO falls within the period of four years from the original DCCO.
C If the revised DCCO falls within the period of three years from the original DCCO.
D If the revised DCCO falls within the period of two years from the original DCCO.
E None of the above