Question

PQR Ltd consumes a minimum of 1250 units in 4 weeks while the average rate of consumption per week is 625 units. If it takes 4 weeks on average for the supplier to deliver the inventory, what should be the re-order level for PQR Ltd?

A 1250
B 2500
C 3750
D 5000
E None of the above