Question
In the given question, four alternatives are given for
the Idiom/ Phrase given in bold in the sentence. Choose the alternative which best expresses the meaning of the Idiom/ Phrase. If none of the given meanings is correct, then mark option 5, i.e., ‘None of the above’ as your answer. The plan will gradually get the company the revenue that they need to sustain in this market but you need to learn to walk before you run .Solution
The idiom "walk before you run" means to start with the basics or to take small, manageable steps before attempting more difficult tasks. It emphasizes the importance of gradual progress rather than rushing into things. In this context, it suggests that the company needs to build up its revenue slowly and steadily. Therefore, B) to progress gradually best expresses the meaning of the idiom.
A alone can complete a work in 18 days and B alone can complete it in 27 days. They work together for 6 days and then B leaves. In how many more days wi...
- Rahul does half the work done by Karan in 2/3 of the time. If they together can complete the work in 14 days, how much time will Karan take to complete the...
‘A’ alone can do some work in 20 days. ‘B’ and ‘C’ together can do the same work in 15 days. If ‘B’ is half as efficient as ‘A’, the...
Ashish and Anil can do a piece of work in 18 days and 24 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete th...
Akhil and Nikhil together can complete a work in 9 days while Nikhil alone takes 12 days to complete 50% of the work. If the efficiency of Sachin is 20%...
- 45 engineers working 5 hours a day take 15 days to complete a project. How many engineers working for 4 hours a day are needed to complete three times the ...
A, B, and C can complete a job in 15, 20, and 30 days, respectively. They start the work together but after 3 days, A leaves. Then, B works alone for 5...
P and Q together can finish a task in 72 days while Q and R can do it in 48 days. If P worked for 18 days, Q worked for 30 days, and then R finished the...
- 'Amit', 'Ravi', and 'Neha' can finish a piece of work in 66, 99, and 132 days respectively. They all started the work, but Amit left 8 days before the work...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alo...