printed in bold and are numbered. Of these, the positions of two of these words may be incorrect and need to be exchanged to make the sentence correct. Find the two words that need to be exchanged. In case the given sentence is correct, your answer is e, i.e., 'No correction required'. The strategy (A) worked tirelessly to develop a effectively (B) marketing team (C) that would comprehensive (D) promote the new product.Solution
The correct arrangement should be: The team worked tirelessly to develop a comprehensive marketing strategy that would effectively promote the new product.
βAβ and βBβ can do a piece of work in 20 days and 32 days, respectively. If they started the work together and worked on it for 5 days, then fin...
20 men can finish a work in 220 days, but at the end of 90 days, 20 additional men are employed. In how many more days will the work be completed?
- Sanya can finish a task by herself in 20 days, while when working together, Riya and Sanya can complete the same task in 10 days. Riya starts the work alon...
Vijay can do a piece of work in 22 days and Sanjay can do the same work in 33 days. If Vijay works for 5 days and got Rs. 1650, and the remaining work w...
The time taken by βAβ to build a wall alone is 50% more than the time taken by him to build it along with βBβ. βBβ will take how much percen...
Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed ...
Time taken by 'A', 'B' and 'C' to complete a work is 51 days, 85 days and 102 days respectively. All of them started the work together but 'B' and 'A' l...
βAβ and βBβ can complete a certain work in 10 days and 15 days, respectively. They started working together and worked till completion of the wo...
Ram can do a piece of work in 12 days and Shyam can do the same work in 16 days. They both started work together, Ram left 2 days before the completion ...
P and Q together can complete 75% of a work in 15 days while Q alone takes 40% more time than P and Q together to complete the whole work. Find the time...