‘X’ can complete a job in 30 days. ‘Y’ is 50% more efficient than ‘X’. How long will they take to finish 75% of the work together?
...Amrita, working alone, can accomplish her sales target in 15 days, while Varshita, working alone, takes ____ days to complete her sales target. If they ...
Choose the statements that correctly show two workers taking 6 hours and 9 hours to complete a task, respectively.
Tony has 3 sons – Harry, Peter and Murphy. Harry and Peter can complete the work in 24 days and 36 days respectively. In how many days Murphy will...
X men can complete the piece of work in 32 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the v...
If 3 men with 4 boys can earn Rs. 2940 in 7 days and 5 men with 9 boys earn Rs. 4620 in 6 days. In how many days will 5 men with 3 boys earn Rs. 118...
25 men can complete a piece of work in 13 days. One man starts the work and after every day one more man joins the work and this continues till the work...
P does one fourth as much work as Q in two third of the time. If together they take 24 days to complete the work, how much time shall Q take to do it?
An elephant can do a work as fast as two horses ‘A’ and ‘B’ can do it by working together. If horse ‘A’ alone can complete the work in 38 ho...
Working individually, 'A' can finish 60% of a task in 18 days, and 'B' takes 15 days longer than 'A' to complete the entire task. However, 'B' and 'C' w...