Question
P, Q and R can do a work in 15, 20 and 30 days
respectively. The contractor decides to put any two of them on the job so as to finish the work earlier. Which of these choices is the best?Solution
The correct answer is D
- The ‘Startup Maharathi’ awards were presented at which event in 2025?
Who manages the Ministry of Rural Development?
What was India’s Human Development Index (HDI) rank in 2023 out of 193 countries?
Which musical instrument does Rakesh Chaurasia, a veteran Indian classical musician, play?
Who was named the Player of the Year for 2023 in the men’s category at the sixth annual Hockey India Awards?
The base year for the Consumer Price Index for Agricultural and Rural Labourers (CPI-AL/RL) has been revised from 1986–87 to:
The RBI revoked the banking licence of Paytm Payments Bank Limited under which section of the Banking Regulation Act, 1949?
Who became the youngest Asian to summit Mount Kilimanjaro in August 2024?
Which panel discussion at the 3rd International Conclave focused on adoption of the UNCITRAL Model Law?
Which life insurance company has announced that the overseas branch of its international subsidiary will now offer US Dollar denominated life and health...