Question
P, Q and R can do a work in 15, 20 and 30 days respectively. The contractor decides to put any two of them on the job so as to finish the work earlier. Which of these choices is the best?
More Previous year papers Questions
- Select the option that can be used as a one-word substitute for the bold segment in the given sentence. Dr. Geller gave a detailed, interesting, and engag...
- In each of the following questions, a sentence is given with a word printed in bold. Choose the option that can best replace the bold word without changing...
- Select the most appropriate ANTONYM of the given word. Renegade
- In the following question, a sentence has been given in Direct/Indirect speech. Out of the four alternatives suggested, select the one which best expresses...
- Rewrite the sentence in Passive voice. The farmer produces wheat.
- In each of the following questions, three statements are given with a phrase or idiom highlighted in bold. You have to select the answer choice that states...
- Find the part of the sentence that contains an error: That the report overlooked several underlying causes (1)/ behind the public unrest were surprising (...
- Spot the grammatical errors in the given sentence. Mark the part with error as your answer. If there is no error, mark "No error" as the answer. (Ignore pu...
- Fill in the blanks with the correct conjunctions: Everybody likes him ________ he is nice and helpful.
- Select the most appropriate option to fill in the blanks. He came to the surface of the water _______ for air.
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)