Question
‘Amit’ is 1.5 times as efficient as ‘Bhuvan’, who is 1/3 as efficient as ‘Chirag’. If Amit and Chirag together complete a work in 18 days, how long will Bhuvan and Dev take to do it if their efficiency ratio is 2:1 respectively?
More Difficult level Section Tests Questions
- The speed ratio of A to B is 4:3. C covers 840 km in 14 hours. If B's speed is 20% lower than C's speed, how much time will A need to cover 512 km?
- A financial institution gives compound interest at the rate of 10% per annum, compounded half yearly. What is the interest earned after one year on a depos...
- A product is bought for Rs. 1,800. The shopkeeper tags it at 25% above the cost price and offers a discount of Rs. 200 at the time of sale. What is the per...
- Which of the following numbers is not a perfect square?
- Calculate the area of the triangle enclosed by the line 3x+6y=18, the x-axis, and the y-axis.
- A total of Rs. 17400 is shared between 'X' and 'Y' in the ratio 11:7. If 'Y' invests his portion in a compound interest scheme at a rate of 10% per annum, ...
- Find the simplified value of the given expression. (-8) x {15 - (-4) x (-5)}
- Ramesh builds 30 chairs in 6 days while Suresh builds 24 chairs in 4 days. How many chairs can both Ramesh and Suresh build in one day together?
- Ravi has 98 marbles of two colours – green and yellow. If he bought 28 more yellow marbles, the ratio of green to yellow marbles would become 3:4. Find how...
- P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 day...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)