      Amit and Anaya can complete a task together in 20 days. If

      Anaya is 150% more efficient than Amit, how many days will Anaya alone take to finish the task?
      A 18 days Correct Answer Incorrect Answer
      B 15 days Correct Answer Incorrect Answer
      C 28 days Correct Answer Incorrect Answer
      D 20 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the efficiency of Amit alone = 4 units/day

      Then, efficiency of Anaya alone = 4 + 4 × 1.5 = 10 units/day

      So, total work = (4 + 10) × 20 = 280 units

      And so, time taken by Anaya alone to complete the work = 280 ÷ 10 = 28 days