Question

The standard cost of labour for 1 unit is 2 hours at ₹50 per hour. Actual production is 100 units and actual labour cost is ₹11,000 for 200 hours. What is the labour rate variance?

A ₹1,000 (A)
B ₹1,000 (F)
C ₹500 (F)
D ₹500 (A)