Question
Statements:All flowers are books. All books are
carpets. Some carpets are keys. Some keys are locks. Conclusions:I. Some keys are books. II. Some keys are flowers. III. Some locks are books. In each question below are given four statements followed by three conclusions numbered I, II and III. You have to take the two given statements to be true even if they seem to be at variance with commonly known facts and then decide which of the given conclusions logically follows from the two given statements, disregarding commonly known factsSolution
All books are carpets(A) + Some carpets are keys(I) ⇒ No conclusion. Hence conclusion I does not follow. All flowers are books(A) + All books are carpets(A) ⇒ All flowers are carpets(A) + Some carpets are keys(I) ⇒ No conclusion. Hence neither conclusion II nor III follows.
A2 type ‘P’ pipes can fill a tank in 450 hours, while B2 type ‘Q’ pipes can fill the same tank in 6...
X can do a piece of work in 25 days. He worked at it for 5 days and then Y finished it in 24 days. In how many days can X and Y together finish the work?
P, Q & R can finish a work in 10 days, 15 days, and 20 days, respectively, working alone. P and Q work on the first day, P and R work on the second day,...
40 laborers were hired to finish a construction job in 50 days. After 35 days of work, only 70% of the job was done. How many additional laborers are ne...
A can do a piece of work in 24 days. B can do the same work in 16 days and C can do the same work in 5/4th time required by both A and B together. A an...
A alone can do a piece of work in 10 days and B alone in 15 days. In how many days will they finish the work together?
12 man can make a wall in 6 days. How many men required to complete the same work in 3 days ?
P and Q can complete a work in 36 days and 54 days, respectively. P, Q and R together can complete the work in 18 days. If R get a total wage of Rs. 594...
P and Q can separately finish the work in 15 days and 25 days respectively. They worked together and P left the work, so Q complete the remaining work i...
It takes a team of either 20 boys or 35 girls, 27 days to achieve a sales target. How many days will it take for a team consisting of 21 boys and 42 gir...