Question
Who lives in flat 1 of the bottommost
floor? Answer the questions based on the information given below. 12 persons M-X live in a building, which consists of four floors such that the bottommost floor is numbered 1 and the topmost floor is numbered 4. Each floor has three types of flats (Flat 1, flat 2 and flat 3) such that flat 1 is to the west of flat 2, which is to the west of flat 3. Flat 3 of floor 4 is immediately above flat 3 of floor 3, Similarly, flat 2 of floor 4 is immediately above flat 2 of floor 3 and so on. Only one person lives in each flat. Each of the flat is of equal dimension. M lives in flat 2 on an odd numbered floor. Q lives above M in the same type of flat and to the east of R. R doesn’t live on floor 3. O and T live in the same type of flat such that O lives immediately above T but below floor 3. O lives in south east of R. V lives to the west of O. V and S live in the same type of flat and V lives immediately above S. S doesn’t live in flat 1. N and U live in the same type of flat such that N lives immediately above U but not in flat 1. Floor number on which X lives is higher than P, whose floor number is higher than W.Solution
1. M lives in flat 2 on odd numbered floor. 2. Q lives above M in the same type of flat and to the east of R. 3. R doesn’t live on floor 3. So, M lives on flat 2 of floor 3 or flat 2 of floor 1. Case U: M lives on flat 2 of floor 3: 4. O and T live in the same type of flat such that O lives immediately above T but below floor 3. 5. O lives in southeast of R. 6. V lives to the west of O. V and S live in the same type of flat and V lives immediately above S, this is not possible in case II(b), so case II(b) is rejected. 7. S doesn’t live in flat 1, so case II(a) is rejected. So, V lives in flat 2 of floor 2 and S lives in flat 2 of floor 1. O and T lives in flat 3.
15 men can do a piece of work in 10 days working 12 hours a day. How many men can do double the work in 25 days working 8 hours a day?
A alone can do a piece of work in 10 days and B alone in 15 days. In how many days will they finish the work together?
A does 1/2 work and B does 3/4 work in the same time. Difference between number of days taken by A and B to work alone to complete the work individually...
Ajay and Bheem collectively earned Rs.9,000 for completing a task, with Bheem's share being Rs.3,000. If Bheem can complete the work on his own in 48 da...
A, B and C alone can complete a work in 30, 60 and 45 days respectively. All of them started working together but after 3 days from start A left the job...
Mohan, Sohan, and Rohan alone can finish a piece of work in 50, 100, and 150 days respectively. They start the work together, but Mohan leaves after 8 d...
12 children and 18 men complete an artwork in 9 days. Each child takes twice as long as a man to finish the artwork. How many days will it take for 18 m...
A group of 24 men is capable of finishing a task in 15 days. Initially, 12 men begin the job and work on it for 12 days. After this period, an additiona...
Billy, Tony and Mike were three workers, employed by a Contractor. They completed the whole work in 20 days. Initially all of them worked together, but ...
Pawan can finish a task in 28 days, while Bhavna requires 7 more days than Pawan to complete the same task. They both started wor...