Question
Which one of the following is the specialization of
Rahul? Study the following information carefully and answer the questions given beside. For submitting the progress report after supervision of the project, seven senior engineers namely - Rahul, Rohit, Kanika, Pramesh, Deeksha, Zishan and Himanshu visit ISRO on four days –Tuesday, Friday, Saturday and Sunday – in a week. At least one engineer but not more than two Engineers visit ISRO on each of these days. Each of them is a specialist in different fields – Electronics, Mechanical, Mechatronics, Programmer, Electrical, Civil and Instrumentation. Pramesh visits on Saturday with civil engineer. Electrical engineer does not visit on Sunday neither with Deeksha nor with Himanshu. Instrumentation engineer Zishan visits alone on Tuesday. Rohit visits on Friday and he is not electrical engineer. Kanika visits on Friday. Himanshu is not civil engineer. Electrical engineer visits with the Electronics engineer. The mechatronics engineer visits on Saturday. Rahul is neither Mechanical nor Civil engineer.Solution
Instrumentation engineer Zishan visits alone on Tuesday. Rohit visits on Friday and he is not electrical engineer. Pramesh visits on Saturday with civil engineer. Kanika visits on Friday. The mechatronics engineer visits on Saturday. Therefore, Pramesh is mechatronics engineer. Electrical engineer does not visit on Sunday neither with Deeksha nor with Himanshu. Electrical engineer visits with the Electronics engineer. Himanshu is not civil engineer. Rahul is neither Mechanical nor Civil engineer. So, the only left Deeksha is civil engineer. Rahul is neither mechanical nor civil engineer; hence, he should be the programmer.
P and Q can finish a job working together in 24 days. P completes two-thirds of the task in 'd' days, and Q finishes the rest in ...
50 children can decorate a hall in 25 days. If 25 children began decorating and after 10 days ‘z’ additional children joined, completing the decorat...
Ratio of the work done by P, Q and R in one day is 7:3:8 respectively. They all together can complete the work in 42 days. Q and R worked on it for 21 d...
- ‘Neha’ can complete a task in 90 days. She worked for 54 days and then left. The rest of the task was completed by ‘Karan’ in 24 days. How much tim...
"Amit" and "Bhanu" have respective completion times of 20 and 30 days for a task. They began working together on the project, but after a few days, "Ami...
Komal and Seema individually can complete a task in ‘3a’ hours and ‘5a’ hours respectively. If they together can complete (2/3)rd of the work in...
M, N and O can complete a task in ‘t’, 100, and ‘t + 20’ days respectively. All three started together, but after 15 days, N dropped out. Then, ...
‘A’ can do 30% of the work in 12 days. ‘B’ can do the whole work in 50 days. Find the time taken by them together to do 75% of the work.
...Time taken by 'X' and 'Y' to complete a work alone is 72 days and 120 days respectively. Find the time taken by 'X' and 'Y' together to complete 25% of ...
- 18 workers can complete 9 tasks in 24 hours. Find the time required by 12 workers to finish 15 tasks.