Question
What is the colour of the
Shirt? Read the following information and answer the questions that follow: 1. In a garment shop, 8 different types of garments viz. Lehenga, Saree, Dupatta, Kurta, Shirt, Sherwani, Skirt and suit having different colours viz. Red, Blue, Green, Pink, Purple, Yellow, Orange, Black are made of four different fabrics i.e. Chanderi, Net, Neoprene, Georgette are kept one above the other. The topmost position being 1. 1. Exactly two garments are made out of one fabric. 2. Garments made of neoprene fabric are vertically adjacent. 3. Neither Green nor black colored garments are made of neoprene or chanderi. 4. The material of the topmost and the bottom most garment is the same. 5. The orange skirt is neither made of net nor georgette and occupies the topmost position. 6. The Red garment is immediately below the garment made of Net. The blue garment is exactly in the middle of Black and purple garment. The saree is made of neoprene and is immediately above the blue kurta. 7. The lehenga is made of net and is in the top three positions. 8. The georgette suit is immediately above saree. 9. Green georgette dupatta is immediately below the pink garment. 10. The pink garment is of net fabric. Garments made of net fabric are kept at even numbered positions. Both neoprene garments lie between net garments. 11. One of the neoprene garments is blue in colour. None of the neoprene garments is purple in colour. Shirt is not pink in color.Solution
We know from 1, 2 Neoprene Neoprene 4, Green – Net/Georgette Black – Net/Georgette 5, Orange – Skirt – Chanderi/neoprene but, the topmost and the bottommost fabrics are same and neoprene garments are vertically adjacent to each other. Thus, cannot be neoprene. Thus, is chanderi. 6, Net immediately above Red. Net Red – Blue in the middle of Black and purple. Black | Blue | Purple Neoprene – saree - Kurta - Blue 8, Georgette – Suit Neoprene – Saree - Kurta - Blue 9. Pink – Net Green – Geogette – dupatta Since, net garments only at even numbered positions, 2nd position reserved for Lehenga The only positions left for another net garment are 4 and 6. Since neoprene garments have to be vertically adjacent to each other, kurta must be of neoprene. Georgette – Suit Neoprene – Saree Neoprene - Kurta - Blue From, 10, both neoprene garments lie between net garments, which is possible only if net is at 6th position. Placing the garments in the known order. The only fabric left is georgette at 7th position.
Since, net is immediately above red, one of the georgettes is red. Blue is immediately between black and purple. Garment at position 5 is blue. Thus, i) Either garments at positions 4 & 6 are black and purple ii) Or garments at positions 3 and 7 are black and purple iii) Or garments at positions 2 and 8 are purple and black i) is possible if 4 is purple and 6 is black (Neoprene cannot be black) ii) is possible if either 3 is black and 7 is purple or 3 is purple and 7 is black None of the cases of (ii) are possible as, one of the georgette garments must be red. Thus case (ii) is discarded. Either 4 & 6 are purple and black Or 2 & 8 are purple and black None of the neoprene garments is purple. Thus garment at 4th position can neither be purple nor black. Thus only one case left, 2 and 8 purple and black. One of the nets is pink (given).According to 9, green gorgette dupatta below pink.
βAβ alone can complete a work in 50 hours. βAβ started the work alone and left after working on it for 10 hours. If βBβ completed the rest o...
40 tailors can stitch a batch of dresses in 30 days. If 20 tailors started the job and after 15 days βuβ more tailors joined them such that the rema...
A can complete a piece of work in 10 days and B can complete it in 15 days. They start working together, but B leaves after 3 days. In how many more day...
- An organization engaged 16 workers to complete a task in 24 days. After 9 days, 6 workers had to leave unexpectedly. How many additional days will it now t...
A contractor planned to complete a project in 5 days by employing βaβ workers. But every day exactly 15 workers were absent. As a result, the work g...
Arjun and Sameer can complete a job in 20 days and 25 days respectively. When Arjun, Sameer, and Nikhil work together, they finish it inΒ
M, N and O can complete a task in βtβ, 100, and βt + 20β days respectively. All three started together, but after 15 days, N dropped out. Then, ...
(x + 7) workers finish 60% of a job in 9 days working 4 hours/day. The remaining work is done by (x + 3) workers in 12 days working 3 hours/day. Find x.
A work can be completed by βAβ and βBβ, alone in 10 days and 12 days, respectively. Find the number of days taken by βCβ to complete the sam...
A piece of work consists of 360 identical units. A can do (x + 4) units per day and B can do (x β 2) units per day. They work together for 9 days and ...