Question
Study the given pattern carefully and select the number
that can replace the question mark [?] in it.First row: 6, 5, 191Second row: 8, 7, 463Third row: 9, 10, [?] (NOTE: Operations should be performed on the whole numbers, without breaking down the number into its constituent digits. For example, 13 - Operations on 13 such as adding/deleting/multiplying etc. to 13 can be performed. Breaking down 13 into 1 and 3 and then performing mathematical operations on 1 and 3 is not allowed.)Solution
The logic followed here is as follows: Third number = (First number)³ - (Second number)²
First row: 6³ - 5² = 216 - 25 = 191
Second row: 8³ - 7² = 512 - 49 = 463
Third row: 9³ - 10² = 729 - 100 = 629
'Ramesh' can complete a work in 40 days. He started the work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. F...
The amount of work completed by 24 men in 5 hours is equivalent to the work done by 21 women in 8 hours. A team of 33 men, working 6 hours daily, can fi...
There is enough food in a camp to last for 30 days if each of the 100 soldiers present at the camp eat 3 times a day. After 20 days, 50 soldiers left t...
‘A’ and ‘B’ can do a piece of work in 15 days and 20 days, respectively. They started working together but ‘A’ left after 3 days. Find the t...
Ajay, Bablu and Chirag can complete a certain work in 21, 28 and 15 days respectively. Ajay and Chirag started the work while Bablu joined them after 5 ...
Akhil and Nikhil together can complete a work in 9 days while Nikhil alone takes 12 days to complete 50% of the work. If the efficiency of Sachin is 20%...
‘X’ is 25% more efficient than ‘Y’, and ‘Z’ is 25% less efficient than ‘Y’. Together, they can complete a job in 40 days. If X and Y wor...
P can do a piece of work in 20 days, Q can complete double the work in 40 days and R can do the work in 30 days. If all of them together earn Rs. 3200, ...
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alon...
A can complete a piece of work in 12 days and B can complete the same work in 18 days. They work together for 4 days and then leave the remaining work ...