Question
Statements: A $ B @ D & E @ G % H, F & A, G $
J Conclusions: I.F & E II. J # B In the following questions, the symbols @, #, %, & and $ are used with the following meaning as illustrated below: 'A @ B' means 'A is not greater than B'. 'A # B' means 'A is neither smaller than nor equal to B'. 'A % B' means' A is not smaller than B'. 'A & B' means 'A is neither greater than nor equal to B'. 'A $ B' means 'A is neither smaller than nor greater than B'. Now in each of the following questions assuming the given statements to be true, find which of the two conclusions I and II given below them is/are definitely true and give your answer accordingly.Solution
Decoded statement : A = B ≤ D < E ≤ G > H, F < A, G = J Decoded conclusion : I. F < E II. J > B Combined Inequalities: F < A = B ≤ D < E ≤ G = J F < A = B ≤ D < E ≤ G = J > H F < E. Hence conclusion I is true. F < A = B ≤ D < E ≤ G = J > H J > B. Hence conclusion II is true.
- A team of 15 workers was assigned to complete a task in 30 days. After working together for 20 days, they discovered that only half of the work had been co...
A and B are capable of completing a project individually in 40 days and 50 days, respectively. Initially, A and B collaborated on the project, and after...
Krishna can do a piece of work in 25 days. He alone worked at it for 10 days and then Balram completed alone the rest work in 20 days. In how many days,...
Akash can finish a task alone in 24 days, while Akash and Bittu working together can complete the same task in 14 days. If Bittu ...
- A can complete 1/4th of a work in 5 days while B can complete 1/5th of the same work in 6 days. In how many days both of them together can complete the who...
Team A can built a project in 4 hours less than the time taken by Team B to built the same project.
The ratio of the strength of Team A to that o...
- 25 employees working 9 hours a day take 20 days to complete a project. How many employees working for 8 hours a day are needed to complete twice the given ...
30 men can complete a task in 160 days. 12 men start the work and manage to do half of it. Then, 18 more men are added to the team to help finish the wo...
Calculate the number of days it would take for a team of 8 boys, 5 girls, and 5 children to Construct a building. This building was previously constru...
Working in a shift of 5 hours 39 workers take 12 days to build a stretch of highway. In how many days will 30 workers working 6 hours a day, complete th...