Question
Worker 'A' can complete the entire task alone in 12.5
days, while worker 'B' can finish it in 25 days. If they take turns working on the task each day, with 'B' starting on the first day, how many days will it take for them to complete the work together?Solution
Let the total work be 25 units (LCM of 12.5 and 25)
Efficiency of 'A' = (25/12.5) = 2 units/day
Efficiency of 'B' = (25/25) = 1 unit/day
Work done by them in first 2 days = 1 + 2 = 3 units
Work done by them in first 16 days = 3 X 8 = 24 units
Remaining work = 25 - 24 = 1 unit
Time taken by 'B' to complete remaining work = (1/1) = 1 day
Therefore, required time = 16 + 1 = 17 days
NPS for traders provide a monthly minimum assured pension of what amount after attaining the age of 60 years?
Consider the following Statements.
I-Â Â Â Â Â Â Â Â Â Â Â Â NEP-2020 advocates for greater internationalisation in education by creating ave...
What does the e-NAM platform offer to buyers and traders to enhance transparency in trading?
Which of the following is FSSAI’s initiative to create safe, healthy, and sustainable food environments within various institutions and workplaces?
Which of the following is the Implementing Agency of UJALA Scheme?
What is the highest inflation tolerance band as agreed by the RBI and the Government of India?
The goal of the Jal Jeevan Mission mission is to provide ______ of water per person per day to every rural household through Functional Household Tap C...
Consider the following Statements.
(I) PM-KMY Scheme is applicable to all small and marginal farmers.
(II) Small and marginal farmers...
Which entity won the SKOCH ESG Award 2024 in the 'Renewable Energy Financing' category?
The BHIM (Bharat Interface for Money) app, launched under the Digital India Mission, primarily aims to: