Let the total work be 25 units (LCM of 12.5 and 25)
Efficiency of 'A' = (25/12.5) = 2 units/day
Efficiency of 'B' = (25/25) = 1 unit/day
Work done by them in first 2 days = 1 + 2 = 3 units
Work done by them in first 16 days = 3 X 8 = 24 units
Remaining work = 25 - 24 = 1 unit
Time taken by 'B' to complete remaining work = (1/1) = 1 day
Therefore, required time = 16 + 1 = 17 days
As per the Motor Vehicles Act any person aggrieved by an award of a Claims Tribunal may, within _____________ from the date of the award, prefer an appe...
Pardon may be tendered to an accomplice under Section 306 CrPC when
The total number of Council of Ministers shall
Criminal breach of trust deals with
Who has the power to audit the accounts of the Authority under the IRDA Act?
What is private document?
According to Section 2(1)(g) of the Arbitration & Conciliation Act 1996 - “legal representative” means-
No suit under Section 6 of the Specific Relief Act, 1963 shall be brought:
The court may frame the issues from the materials:
Which of the following is not a formal source of Muslim personal law in India?
A. The Constitution of India
B. The Quran
C. Su...