Question
Worker 'A' can complete the entire task alone in 12.5
days, while worker 'B' can finish it in 25 days. If they take turns working on the task each day, with 'B' starting on the first day, how many days will it take for them to complete the work together?Solution
Let the total work be 25 units (LCM of 12.5 and 25)
Efficiency of 'A' = (25/12.5) = 2 units/day
Efficiency of 'B' = (25/25) = 1 unit/day
Work done by them in first 2 days = 1 + 2 = 3 units
Work done by them in first 16 days = 3 X 8 = 24 units
Remaining work = 25 - 24 = 1 unit
Time taken by 'B' to complete remaining work = (1/1) = 1 day
Therefore, required time = 16 + 1 = 17 days
According to the Solow Model, which factor is primarily responsible for sustained economic growth in the long run?
The PM-PRANAM scheme, highlighted in recent fiscal cycles, primarily aims to:
Real Wages = 500, Consumer price index = 1.2. Calculate nominal wages?
Elistan can produce either 5 monster trucks or 10 cans of silly string in a day. What is the opportunity cost of one can of silly string?
In a regression analysis, if the total sum of squares (SST) is 250 and the explained sum of squares (SSR) is 200, the coefficient of determination (Rยฒ)...
If a government defaults on the value of its debt by 3/4, this is the same as imposing a ____ tax on interest and repayment of the principal.
The Phillips curve shows the trade-off between ----- and -----?
Under a flexible exchange rate regime, an expansionary monetary policy will most likely lead to:
For the given data, n=20, Xฬ = 40, Yฬ = 60, โ(X-10)2 = 100, โ(Y-30)2 =160 andย ย ย ย โ(X-10)*(Y-30) = 80. Calculate the r...