      Worker 'A' can complete the entire task alone in 12.5

      days, while worker 'B' can finish it in 25 days. If they take turns working on the task each day, with 'B' starting on the first day, how many days will it take for them to complete the work together?
      A 15 days Correct Answer Incorrect Answer
      B 17 days Correct Answer Incorrect Answer
      C 17.5 days Correct Answer Incorrect Answer
      D 16.5 days Correct Answer Incorrect Answer

      Solution

      Let the total work be 25 units (LCM of 12.5 and 25)
      Efficiency of 'A' = (25/12.5) = 2 units/day
      Efficiency of 'B' = (25/25) = 1 unit/day
      Work done by them in first 2 days = 1 + 2 = 3 units
      Work done by them in first 16 days = 3 X 8 = 24 units
      Remaining work = 25 - 24 = 1 unit
      Time taken by 'B' to complete remaining work = (1/1) = 1 day
      Therefore, required time = 16 + 1 = 17 days