Question
A contractor hires 12 workers to complete a project in
20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. How many days would it have taken if only 12 workers were employed?Solution
Work done in 8 days by 12 workers = 8 × 12 = 96 units. Remaining work = Total work - 96 = (12 × 20 - 96) = 144 units. New workers = 12 + 4 = 16 workers. Time taken by 16 workers = 144/16 = 9 days. If only 12 workers were employed, time = (96 + 144)/12 = 20 days. Correct answer: c) 20 days
Consider the following Statements about PLFS and choose the option with correct Statements.
(I)- PLFS estimates the key employment and unemplo...
The Ministry of Defence signed MoUs with which banks to onboard them as SPARSH Service Centres?
According to the Economic Survey 2024–25, India’s real GDP growth projection for FY26 lies between:
The PM Vishwakarma scheme also includes a dedicated portal for:
Which of the following Development Round of WTO was held in 2001?
NISHTHA Programme is one of the significant programmes that us aimed at changing the education scenario of our country. Who are the beneficiaries of the...
Which of the following is the prime utility of UMANG App?
Which of the following statements accurately reflect the interconnectedness of the Sustainable Development Goals (SDGs)?
Statement A: Achievin...
What is the percentage of Adjusted Net Banking Credit (ANBC) that domestic banks are required to lend to the weaker section according to the lending re...
What is the expected role of nuclear energy in India's future energy mix as mentioned in the Union Budget 2024-25?