πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A contractor hires 12 workers to complete a project in

      20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. How many days would it have taken if only 12 workers were employed?
      A 22 days Correct Answer Incorrect Answer
      B 25 days Correct Answer Incorrect Answer
      C 20 days Correct Answer Incorrect Answer
      D 28 days Correct Answer Incorrect Answer

      Solution

      Work done in 8 days by 12 workers = 8 Γ— 12 = 96 units. Remaining work = Total work - 96 = (12 Γ— 20 - 96) = 144 units. New workers = 12 + 4 = 16 workers. Time taken by 16 workers = 144/16 = 9 days. If only 12 workers were employed, time = (96 + 144)/12 = 20 days. Correct answer: c) 20 days

      Practice Next
      ask-question