Question
A contractor hires 12 workers to complete a project in
20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. How many days would it have taken if only 12 workers were employed?Solution
Work done in 8 days by 12 workers = 8 ├Ч 12 = 96 units. Remaining work = Total work - 96 = (12 ├Ч 20 - 96) = 144 units. New workers = 12 + 4 = 16 workers. Time taken by 16 workers = 144/16 = 9 days. If only 12 workers were employed, time = (96 + 144)/12 = 20 days. Correct answer: c) 20 days
When entering text within a document, the Enter key normally pressed at the end of every
In the question below, few statements are given depicting an issue or a problem. You have to assume everything in the statements to be true even if the...
рдордиреАрд╖ 3 рдорд╛рд░реНрдЪ 1980 рдХреЛ рдкреИрджрд╛ рд╣реБрдЖ рдерд╛ред рд╕рдВрдЬреАрд╡ , рдордиреАрд╖ рд╕реЗ 4 рджрд┐рди рдкрд╣рд▓реЗ рдкреИрджрд╛...
A __________ is the component which routes data between the computer's buses & Devices, so that all the components which make up the computer can commun...
The marks obtained by Meena in English is 40% more than the marks obtained by her in History, and the average marks scored by Meena in English, History,...
The mean proportion of 289 and 144 is:
Statements : X < Q = I тЙд Y < U тЙд S = W > J = B > R
Conclusions :
I.┬аX < W
II.┬аS > R
DSL is used in _________ connections.
If all the digits of the number 789615432 are arranged in decreasing order, then sum of 5 th and 6 th digits (from the left end) of the number thus form...
Select the option that is related to the third term in the same way as the second term is related to the first term.
Unusual : Frequent :: Righteous :?