Question
A contractor hires 12 workers to complete a project in
20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. How many days would it have taken if only 12 workers were employed?Solution
Work done in 8 days by 12 workers = 8 × 12 = 96 units. Remaining work = Total work - 96 = (12 × 20 - 96) = 144 units. New workers = 12 + 4 = 16 workers. Time taken by 16 workers = 144/16 = 9 days. If only 12 workers were employed, time = (96 + 144)/12 = 20 days. Correct answer: c) 20 days
Which Indian institution is recognized as the apex body for coordinating horticultural research in India?
Ratio of yield of photochemical product to total number of quanta used is called as ___
International Rural Women day is celebrated on ………………
The headquarters directorate of Plant Protection, Quarantine and Storage (DPPQS) is located at which place?
Give the chronological order in the development of following herbicides
A. Atrazine
B. 2, 4-D
C. Bispyribac Sodium
D. Alachl...
Which of the following is used in neutron moisture meter as neutron source?Â
Stalk of a single flower is calledÂ
The enzyme used in the first step of glycolysis is:
Which type of inflorescence is typically observed in onion plants?
Fully opened blossoms in apple may be killed at temperature below