Question
A contractor hires 12 workers to complete a project in
20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. How many days would it have taken if only 12 workers were employed?Solution
Work done in 8 days by 12 workers = 8 ├Ч 12 = 96 units. Remaining work = Total work - 96 = (12 ├Ч 20 - 96) = 144 units. New workers = 12 + 4 = 16 workers. Time taken by 16 workers = 144/16 = 9 days. If only 12 workers were employed, time = (96 + 144)/12 = 20 days. Correct answer: c) 20 days
walking inflation
рджрд┐рдП рдЧрдП рд╡рд┐рдХрд▓реНрдкреЛрдВ рдореЗрдВ рд╕реЗ рд╡рд╣ рд╡рд╛рдХреНрдп рдЪреБрдиреЗ рдЬреЛ рдкреНрд░рд╢реНрди рдореЗрдВ рджрд┐рдП ...
рджрд┐рдП рдЧрдП рдкреНрд░рддреНрдпреЗрдХ рдкреНрд░рд╢реНрди рдореЗрдВ рдПрдХ рд╣рд┐рдВрджреА рдХрд╛ рд╡рд╛рдХреНрдп рджрд┐рдпрд╛ рдЧрдпрд╛ я┐╜...
рджрд┐рдП рдЧрдП рд╢рдмреНрджреЛрдВ рдореЗ рд╕реЗ рдХреМрди рд╕рд╛ рд╢рдмреНрдж тАЬ рдирдХрд╛рд░рдирд╛ тАЭ рдХрд╛ рд╕рд╣реА рдЕрд░реНрде рдирд╣реАрдВ я┐╜...
рдирд┐рдореНрди рд╣рд┐рдиреНрджреА рд╢рдмреНрджреЛрдВ рдХрд╛ рд╕рд╣реА рдЕрдБрдЧреНрд░реЗрдЬреА рд╢рдмреНрджрд╛рд░реНрде рдмрддрд╛рдПрдВ-
...Testamentary рд▓рд┐рдП рд╕рд╣реА рдкрд╛рд░рд┐рднрд╛рд╖рд┐рдХ рд╢рдмреНрдж рд╣реИ ?
рдиреАрдЪреЗ рджрд┐рдП рдЧрдП рд╢рдмреНрджреЛрдВ рдореЗ рд╕реЗ рдХреМрди рд╕рд╛ рд╢рдмреНрдж “рдЙрддреНрдкрд╛рдж рд╢реБрд▓реНрдХ” рдХрд╛ рд╕...
The following Hindi sentences are followed by four different ways in which they can be paraphrased in English language. Identify the option wh...
рд▓рдЧреЗ рдкреНрд░рддрд┐рдмрдВрдзреЛрдВ рд╕реЗ рд╡реНрдпрд╛рдкрд╛рд░ рдореЗрдВ рд╡реНрдпрд╡рдзрд╛рди рдиреЗ рдЖрдкреВрд░реНрддрд┐ рдХреА рдЪрд┐рдВрддя┐╜...
рдирд┐рдореНрдирд▓рд┐рдЦрд┐рдд рдЕрдВрдЧреНрд░реЗрдЬреА рд╡рд╛рдХреНрдп рдХрд╛ рд╣рд┐рдВрджреА рдореЗрдВ┬а рд╕рд╣реА рдЕрдиреБрд╡рд╛рдж рдЪреБрдирд┐рдП...