Question
A contractor hires 12 workers to complete a project in
20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. How many days would it have taken if only 12 workers were employed?Solution
Work done in 8 days by 12 workers = 8 × 12 = 96 units. Remaining work = Total work - 96 = (12 × 20 - 96) = 144 units. New workers = 12 + 4 = 16 workers. Time taken by 16 workers = 144/16 = 9 days. If only 12 workers were employed, time = (96 + 144)/12 = 20 days. Correct answer: c) 20 days
The silk fibres are held together in cocoon by a substance known as……………………
Saline soils could be improved by:-
Largest soil order in world is
During a prolonged dry spell, a farmer notices soil crusting in the field. What could be a possible consequence of soil crusting on the crops?
What is soil sickness?
What is the primary function of humus in soil?
Which of the following groups of nutrients is absorbed by plants only in anionic form?
………………………….. is designed to break up hard layers or pans without bringing them to the surface.
...When the contact of soil moisture still decreased below the wilting point in way that the water is held very tightly & may be state of vapour around soi...
According to USDA classification of salt affected soils; a soil having EC >4 mmho/cm; ESP >15; pH